Suncor Firebag COGEN – Firewater Expansion

Project Owner:   Suncor Energy Inc.

Project Location:   Suncor FirebagSite

Project Date:   August – October 2007

Project Manager:   D.J. Grant

Project Description: 

Upgrades to the existing firewater system were required to provide fire protection for Suncor’s cogeneration facility and administration complex. The scope of work consisted of excavation, fabrication, installation, testing, and backfill of new firewater system within an existing network of live high voltage electrical utilities. Working closely with TransAlta, the utility crossings were completed safely and the project was completed on schedule.