Project Owner: Suncor Energy Inc.
Project Location: Suncor Voyageur Site – Fort McMurray, AB
Project Date: October 2011 – September 2013
Project Manager: D.J. Grant
Project Description:
Suncor’s effort to restart construction on the Voyageur Upgrader Project began with the execution of earthworks for the South Lodge, North Lodge and Central Lodge camp sites. The activities included site clearing, muskeg removal, clay borrow for pad and road construction, site drainage, firewater pond construction, supply and installation of deep and shallow underground utilities.
The three lodges will serve as temporary facilities to accommodate the labour force required for the Voyageur Project.